[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109101":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1109101,783,1,"单选题","监测单位应当编制监测方案。监测方案由监测单位技术负责人审核签字并加盖单位公章，报送（ ）后方可实施。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设单位",false,{"key":16,"text":17,"correct":18},"B","监理单位",true,{"key":20,"text":21,"correct":14},"C","质量监督机构",{"key":23,"text":24,"correct":14},"D","质量检测机构","本题考查的是现场安全管理。监测单位应当编制监测方案。监测方案由监测单位技术负责人审核签字并加盖单位公章，报送监理单位后方可实施。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]