[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109092":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1109092,783,1,"单选题","平行检验的项目、数量、频率和费用等应符合建设工程监理合同的约定。对平行检验不合格的施工质量，项目监理机构应( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","签发监理通知单，要求施工单位限期将其撤出施工现场",false,{"key":16,"text":17,"correct":18},"B","签发监理通知单，要求施工单位在指定的时间内整改并重新报验",true,{"key":20,"text":21,"correct":14},"C","签发工程暂停令，责令施工单位暂停下一工序施工",{"key":23,"text":24,"correct":14},"D","签发工程暂停令，责令施工单位按设计处理文件进行修复","对平行检验不合格的施工质量，项目监理机构应签发监理通知单，要求施工单位在指定的时间内整改并重新报验。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]