[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109087":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1109087,783,1,"单选题","在工程质量控制方面，项目监理机构发现( )，应及时签发监理通知单，要求施工单位整改。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工存在重大质量隐患的",false,{"key":16,"text":17,"correct":18},"B","施工单位采用不适当的施工工艺的",true,{"key":20,"text":21,"correct":14},"C","施工单位未按审查通过的工程设计文件施工的",{"key":23,"text":24,"correct":14},"D","施工单位拒绝项目监理机构管理的","项目监理机构签发监理通知单时，应要求施工单位在发文本上签字，并注明签收时间。施工单位应按监理通知单的要求进行整改。整改完毕后，向项目监理机构提交监理通知回复单。项目监理机构应根据施工单位报送的监理通知回复单对整改情况进行复查，并提出复查意见。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]