[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109049":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1109049,783,1,"单选题","施工方案的审查包括程序性审查和内容性审查，下列关于程序性审查的描述中，正确的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","重点核对审批人是否为项目技术负责人",false,{"key":16,"text":17,"correct":14},"B","施工方案应由项目经理组织编制",{"key":19,"text":20,"correct":14},"C","应重点审查施工方案的校对人是否符合有关权限规定的要求",{"key":22,"text":23,"correct":24},"D","施工方案应由施工单位技术负责人审批签字后提交项目监理机构",true,"2020版教材P112 程序性审查应重点审查施工方案的编制人、审批人是否符合有关权限规定的要求。根据相关规定，通常情况下，施工方案应由项目技术负责人组织编制，并经施工单位技术负责人审批签字后提交项目监理机构。项目监理机构在审批施工方案时，应检查施工单位的内部审批程序是否完善、签章是否齐全，重点核对审批人是否为施工单位技术负责人。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]