[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109048":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1109048,783,1,"单选题","经审查批准的施工组织设计，不得擅自任意改动。若需进行实质性的调整、补充或变动，应报（ ）审查同意。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工单位工程技术负责人",false,{"key":16,"text":17,"correct":14},"B","项目经理",{"key":19,"text":20,"correct":21},"C","项目监理机构",true,{"key":23,"text":24,"correct":14},"D","建设单位","2020版教材P109-111 经审查批准的施工组织设计，施工单位应认真贯彻实施，不得擅自任意改动。若需进行实质性的调整、补充或变动，应报项目监理机构审查同意。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]