[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109012":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1109012,783,1,"单选题","（2017年真题）采购过程中的质量控制主要是采购方案的审查及其工作计划中质量要求的确定。设备安装单位直接从市场上采购设备时，采购方案最终应获得（ ）的批准。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","设计单位现场代表",false,{"key":16,"text":17,"correct":14},"B","总承包单位",{"key":19,"text":20,"correct":14},"C","监理单位总监理工程师",{"key":22,"text":23,"correct":24},"D","建设单位",true,"本题考核的是市场采购设备的质量控制。设备采购方案要根据建设项目的总体计划和相关设计文件的要求编制， 设备采购方案最终应获得建设单位的批准。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]