[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109011":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1109011,783,1,"单选题","（2016年真题）建设单位负责采购设备时，控制质量的首要环节是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","编制设备监造方案",false,{"key":16,"text":17,"correct":18},"B","选择合格的供货厂商",true,{"key":20,"text":21,"correct":14},"C","确定主要技术参数",{"key":23,"text":24,"correct":14},"D","选择适宜的运输方式","本题考查的是向生产厂家订购设备质量控制。选择一个合格的供货厂商，是向生产厂家订购设备质量控制工作的首要环节。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]