[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109009":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1109009,783,1,"单选题","在设备制造过程中，如由于设备制造单位需要对设备的设计提出修改时，最终的设计变更应得到（ ）的同意，各方会签后方可实施。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设单位",true,{"key":16,"text":17,"correct":18},"B","原设计单位",false,{"key":20,"text":21,"correct":18},"C","监理单位",{"key":23,"text":24,"correct":18},"D","施工图审查机构","考点:设备制造的质量控制内容。在设备制造过程中，如由于设备订货方、原设计单位、监造单位或设备制造单位需要对设备的设计提出修改时，应由原设计单位出具书面设计变更通知或变更图，并由总监理工程师审核设计变更及因变更引起的费用增减和制造工期的变化。设计变更应得到建设单位的同意，各方会签后方可实施。设计变更不得降低设备质量。参见教材P202。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]