[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109000":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1109000,783,1,"单选题","根据建设项目总体计划和相关设计文件的要求编制的设备采购方案，经（）的批准后方可实施。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","监理工程师",false,{"key":16,"text":17,"correct":14},"B","设计负责人",{"key":19,"text":20,"correct":14},"C","安装单位",{"key":22,"text":23,"correct":24},"D","建设单位",true,"2020版教材P197-198 设备采购方案应根据建设项目的总体计划和相关设计文件的要求编制，以使采购的设备符合设计文件要求。设备采购方案经建设单位的批准后方可实施。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]