[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108996":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108996,783,1,"单选题","建设单位委托监理单位实施设备监造的情况下，设备运往现场前应按要求进行出厂前的检查，符合要求后由( )签认同意后方可出厂。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","原设计负责人",false,{"key":16,"text":17,"correct":14},"B","建设单位代表",{"key":19,"text":20,"correct":21},"C","总监理工程师",true,{"key":23,"text":24,"correct":14},"D","采购方负责人","2020版教材P203 在设备运往现场前，项目监理机构应按设计要求检查设备制造单位对待运设备采取的防护和包装措施，并应检查是否符合运输、装卸、储存、安装的要求，以及相关的随机文件、装箱单和附件是否齐全，符合要求后由总监理工程师签认同意后方可出厂。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]