[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108994":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108994,783,1,"单选题","在设备制造过程中，由于设备订货方对设备的设计提出修改时，应由（）出具书面设计变更通知或变更图。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设单位",false,{"key":16,"text":17,"correct":18},"B","原设计单位",true,{"key":20,"text":21,"correct":14},"C","有资质的其他设计单位",{"key":23,"text":24,"correct":14},"D","订货单位","2020版教材P200-202 在设备制造过程中，如由于设备订货方、原设计单位、监造单位或设备制造单位需要对设备的设计提出修改时，应由原设计单位出具书面设计变更通知或变更图。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]