[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108992":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108992,783,1,"单选题","下列属于设备制造前的质量控制的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","对加工作业条件的控制",false,{"key":16,"text":17,"correct":14},"B","对工序产品的检查与控制",{"key":19,"text":20,"correct":14},"C","对不合格零件的处置",{"key":22,"text":23,"correct":24},"D","审查设备制造的工艺方案",true,"2020版教材P200-202 设备制造前的质量控制包括： (1)熟悉图纸、合同，掌握相关的标准、规范和规程，明确质量要求； (2)明确设备制造过程的要求及质量标准； (3)审查设备制造的工艺方案； (4)对设备制造分包单位的审查； (5)对检验计划和检验要求的审查； (6)对生产人员上岗资格的检查； (7)用料的检查。 选项ABC属于设备制造过程中的质量控制。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]