[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108853":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108853,783,1,"单选题","在工程质量统计分析时，应用控制图观察分析生产状态，应判定为工序异常的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","连续七点链",true,{"key":16,"text":17,"correct":18},"B","排列点连续6点下降",false,{"key":20,"text":21,"correct":18},"C","排列点在连续11点中有6点连续司侧",{"key":23,"text":24,"correct":18},"D","排列点连续5点上升","出现五点链，应注意生产过程发展状况。出现六点链，应开始调查原因。出现七点链，应判定工序异常，需采取处理措施，所以选A。连续7点或7点以上上升或下降排列，就应判定生产过程有异常因素影响，要立即采取措施，所以选项BD错误。在连续11点中有10点在同侧时说明生产过程异常，所以C错误。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]