[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108824":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108824,783,1,"单选题","（2018年真题）对已同意覆盖的工程隐蔽部位质量有疑问的，项目监理机构应（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","要求施工单位报送经设计单位认可的处理方案",false,{"key":16,"text":17,"correct":14},"B","要求施工单位组织专题论证",{"key":19,"text":20,"correct":14},"C","对隐蔽工程进行跟踪检查",{"key":22,"text":23,"correct":24},"D","要求施工单位对该隐蔽部位进行钻孔探测或揭开进行重新检验",true,"本题考核的是工程质量检验制度。对已同意覆盖的工程隐蔽部位质量有疑问的，或发现施工单位私自覆盖工程隐蔽部位的，项目监理机构应要求施工单位对该隐蔽部位进行钻孔探测或揭开或其他方法进行重新检验。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]