[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108801":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108801,783,1,"单选题","总监理工程师在约定的时间内，组织（ ）审查施工单位提交的施工组织设计报审表，提出意见后，由（ ）审核签认。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","监理员，专业监理工程师",false,{"key":16,"text":17,"correct":18},"B","专业监理工程师，总监理工程师",true,{"key":20,"text":21,"correct":14},"C","监理单位技术负责人，总监理工程师",{"key":23,"text":24,"correct":14},"D","总监理工程师，建设单位","2020版教材P42-46 在工程开工前，施工单位必须完成施工组织设计的编制及内部审批工作，填写《施工组织设计\u002F (专项)施工方案报审表》报送项目监理机构。总监理工程师在约定的时间内，组织专业监理工程师审查，提出意见后，由总监理工程师审核签认。需要施工单位修改时，由总监理工程师签发书面意见，退回施工单位修改后重新报审。施工单位应严格按审定的施工组织\u002F施工方案设计文件施工。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]