[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108789":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108789,783,1,"单选题","总监理工程师组织专业监理工程师审查施工单位报送的工程开工报审表及相关资料时，不属于审查内容的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","设计交底和图纸会审是否已完成",false,{"key":16,"text":17,"correct":18},"B","施工许可证是否已办理",true,{"key":20,"text":21,"correct":14},"C","施工组织设计是否已由总监理工程师签认",{"key":23,"text":24,"correct":14},"D","进场道路及水、电、通信等是否已满足开工要求","总监理工程师组织专业监理工程师审查施工单位报送的开工报审表及相关资料；同时具备下列条件时，应由总监理工程师签署审查意见，并应报建设单位批准后，总监理工程师签发工程开工令： ⑴设计交底和图纸会审已完成； ⑵施工组织设计已由总监理工程师签认； ⑶施工单位现场质量、安全生产管理体系已建立，管理及施工人员已到位，施工机械具备使用条件，主要工程材料已落实； ⑷进场道路及水、电、通信等已满足开工要求。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]