[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108785":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108785,783,1,"单选题","工程施工过程中，对已进场但检验不合格的工程材料，项目监理机构应要求施工单位（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","停工整改并封存不合格材料",false,{"key":16,"text":17,"correct":14},"B","征求设计单位对不合格材料的使用意见",{"key":19,"text":20,"correct":21},"C","限期将不合格材料撤出施工现场",true,{"key":23,"text":24,"correct":14},"D","征求检测机构对不合格材料的使用意见","项目监理机构对已进场经检验不合格的工程材料、构配件、设备，应要求施工单位限期将其撤出施工现场。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]