[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108660":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108660,783,1,"单选题","在施工进度计划中，工作之间由于劳动力、施工机械、材料和构配件等资源的组织和安排需要而形成的逻辑关系，称为()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","依次关系",false,{"key":16,"text":17,"correct":14},"B","搭接关系",{"key":19,"text":20,"correct":21},"C","组织关系",true,{"key":23,"text":24,"correct":14},"D","工艺关系","四、几个术语：工艺关系、组织关系、紧前工作、紧后工作、平行工作、先行工作、后续工作、线路、关键线路和关键工作。生产性工作之间由工艺过程决定的、非生产性工作之间由工作程序决定的先后顺序关系称为工艺关系。 工作之间由于组织安排需要或资源(劳动力、原材料、施工机具等)调配需要而规定的先后顺序关系称为组织关系",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]