[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108659":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108659,783,1,"单选题","某工程有3个施工过程，依次为：钢筋→模板→混凝土，划分为Ⅰ和Ⅱ施工段编制工程网络进度计划。下列工作逻辑关系中，属于正确工艺关系的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","模板Ⅰ→混凝土Ⅰ",true,{"key":16,"text":17,"correct":18},"B","模板Ⅰ→钢筋Ⅰ",false,{"key":20,"text":21,"correct":18},"C","钢筋Ⅰ→钢筋Ⅱ",{"key":23,"text":24,"correct":18},"D","模板Ⅰ→模板Ⅱ","考点:工艺关系和组织关系。生产性工作之间由工艺过程决定的、非生产性工作之间由工作程序决定的先后顺序关系称为工艺关系，钢筋Ⅰ→模板Ⅰ→混凝土Ⅰ。参见教材P36",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]