[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108658":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108658,783,1,"单选题","网络图中相对于某项工作而言，可以与该工作同时进行的工作即为该工作的（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","先行工作",false,{"key":16,"text":17,"correct":14},"B","紧前工作",{"key":19,"text":20,"correct":21},"C","平行工作",true,{"key":23,"text":24,"correct":14},"D","紧后工作","考点:紧前工作、紧后工作和平行工作。网络图中，相对于某项工作而言，可以与该工作同时进行的工作即为该工作的平行工作。参见教材P36",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]