[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108656":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108656,783,1,"单选题","双代号网络计划中虚工作的含义是指（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","相邻工作间的逻辑关系，只消耗时间",false,{"key":16,"text":17,"correct":14},"B","相邻工作间的逻辑关系，只消耗资源",{"key":19,"text":20,"correct":14},"C","相邻工作间的逻辑关系，消耗资源和时间",{"key":22,"text":23,"correct":24},"D","相邻工作间的逻辑关系，不消耗资源和时间",true,"考点:网络图的组成。在双代号网络图中，有时存在虚箭线，虚箭线不代表实际工作，称为虚工作。虚工作既不消耗时间，也不消耗资源。虚工作主要用来表示相邻两项工作之间的逻辑关系。参见教材P36。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]