[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108655":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108655,783,1,"单选题","双代号网络图绘制时，应尽量避免网络图中工作箭线的交叉。当交叉不可避免时，可以采用（ ）处理。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","母线法",false,{"key":16,"text":17,"correct":14},"B","S曲线法",{"key":19,"text":20,"correct":21},"C","过桥法",true,{"key":23,"text":24,"correct":14},"D","搭接法","考点:双代号网络图的绘制。双代号网络图绘制时，应尽量避免网络图中工作箭线的交叉。当交叉不可避免时，可以采用过桥法或指向法处理。参见教材P39",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]