[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108653":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108653,783,1,"单选题","在工程网络计划执行过程中，如果某项工作实际进度拖延的时间超过其自由时差，则该工作（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","必定影响其紧后工作的最早开始时间",true,{"key":16,"text":17,"correct":18},"B","必定变为关键工作",false,{"key":20,"text":21,"correct":18},"C","不会影响其后续工作的正常进行",{"key":23,"text":24,"correct":18},"D","不会影响工程总工期","考点:网络计划时间参数的概念。工作的自由时差是指在不影响其紧后工作最早开始时间的前提下，本工作可以利用的机动时间。如果超过自由时差则会影响其紧后工作的最早开始时间。参见教材P45",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]