[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108652":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108652,783,1,"单选题","某网络计划在执行中发现B工作还需作业6天，但该工作至计划最迟完成时间尚有4天，则该工作（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","正常",false,{"key":16,"text":17,"correct":18},"B","影响总工期2天",true,{"key":20,"text":21,"correct":14},"C","影响总工期4天",{"key":23,"text":24,"correct":14},"D","影响总工期6天","考点:网络计划时间参数的概念。工作的总时差是指在不影响总工期的前提下，本工作可以利用的机动时间。超过最迟完成时间就会影响到总工期，所以影响工期为6－4＝2天。参见教材P45。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]