[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108651":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108651,783,1,"单选题","根据网络计划时间参数计算得出的工期称为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","要求工期",false,{"key":16,"text":17,"correct":14},"B","计划工期",{"key":19,"text":20,"correct":21},"C","计算工期",true,{"key":23,"text":24,"correct":14},"D","合同工期","考点:网络计划时间参数的概念。计算工期（Tc）：根据网络计划时间参数计算而得到的工期。要求工期（Tr）：任务委托人所提出的指令性工期。计划工期（Tp）：根据要求工期和计算工期所确定的作为实施目标的工期。参见教材P45。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]