[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108650":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108650,783,1,"单选题","在工程网络计划中，G工作的最早开始时间为第16天，其持续时间为4天，该工作有3项紧后工作，它们的最早开始时间分别为第23天、第24天，第25天，则G工作的自由时差为（ ）天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","2",false,{"key":16,"text":17,"correct":18},"B","3",true,{"key":20,"text":21,"correct":14},"C","4",{"key":23,"text":24,"correct":14},"D","5","考点:双代号网络计划时间参数的计算。根据公式FFi－j＝min{ESj－k－EFi－j}＝min{ESj－k－ESi－j－Di－j}＝min{23－（16＋4），24－（16＋4），25－（16＋4）}＝min{3，4，5}＝3（天）。参见教材P46。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]