[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108649":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108649,783,1,"单选题","在按工作计算法计算双代号网络计划时间参数的过程中，网络计划的计算工期应等于（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","以网络计划终点节点为完成节点的工作的最早完成时间的最大值",true,{"key":16,"text":17,"correct":18},"B","紧前工作最早完成时间的最大值",false,{"key":20,"text":21,"correct":18},"C","网络计划终点节点的最早时间",{"key":23,"text":24,"correct":18},"D","网络计划终点节点的最迟时间","考点:按工作计算法。按工作计算法，是以网络计划中的工作为对象，直接计算各项工作的时间参数。网络计划的计算工期应等于以网络计划终点节点为完成节点的工作的最早完成时间的最大值。参见教材P47。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]