[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108648":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108648,783,1,"单选题","在计算双代号网络计划的时间参数时，工作的最早开始时间应为其所有紧前工作（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","最早完成时间的最小值",false,{"key":16,"text":17,"correct":18},"B","最早完成时间的最大值",true,{"key":20,"text":21,"correct":14},"C","最迟完成时间的最小值",{"key":23,"text":24,"correct":14},"D","最迟完成时间的最大值","考点:双代号工程网络计划时间参数的计算。在计算双代号网络计划的时间参数时，工作的最早开始时间应为其所有紧前工作最早完成时间的最大值。参见教材P47。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]