[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108644":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108644,783,1,"单选题","有 A，B两项连续工作其最早开始时间分别为4天和10天，持续时间分别为4天和5天，则A工作的自由时差是（ ）天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","2",true,{"key":16,"text":17,"correct":18},"B","3",false,{"key":20,"text":21,"correct":18},"C","4",{"key":23,"text":24,"correct":18},"D","5","考点:双代号网络计划时间参数的计算。对于有紧后工作的工作，其自由时差等于本工作之紧后工作最早开始时间减本工作最早完成时间所得之差的最小值。A工作的自由时差=10-（4+4）=2（天）。参见教材P49。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]