[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108643":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108643,783,1,"单选题","下列关于工程网络计划关键工作的表述中，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","双代号网络计划中关键工作两端的节点必为关键节点",true,{"key":16,"text":17,"correct":18},"B","双代号网络计划中两端为关键节点的工作必为关键工作",false,{"key":20,"text":21,"correct":18},"C","工程网络计划中关键工作的自由时差与总时差全部为零",{"key":23,"text":24,"correct":18},"D","关键线路上各项工作的持续时间总和应等于网络计划的计划工期","考点:双代号网络计划时间参数的计算。在双代号网络计划中，关键线路上的节点称为关键节点。关键工作两端的节点必为关键节点，但两端为关键节点的工作不一定是关键工作，所以选项A正确，选项B错误；选项C错误，当计划工期等于计算工期时，总时差为零的工作为关键工作；选项D错误，关键线路上各项工作的持续时间总和应等于网络计划的计算工期。参见教材P50。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]