[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108642":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108642,783,1,"单选题","某分部工程双代号网络计划如下图所示，其关键线路是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","①→③→⑤→⑥",false,{"key":16,"text":17,"correct":18},"B","①→③→④→⑤→⑥",true,{"key":20,"text":21,"correct":14},"C","①→②→③→④→⑤→⑥",{"key":23,"text":24,"correct":14},"D","①→②→③→⑤→⑥","考点:双代号网络计划时间参数的计算。关键线路为①→③→④→⑤→⑥，计算工期为18。参见教材P54。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]