[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108641":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108641,783,1,"单选题","当双代号网络计划的计算工期等于计划工期时，下列关于关键工作的说法错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","关键工作的自由时差为零",false,{"key":16,"text":17,"correct":14},"B","相邻两项关键工作之间的时间间隔为零",{"key":19,"text":20,"correct":21},"C","关键工作的持续时间最长",true,{"key":23,"text":24,"correct":14},"D","关键工作的最早开始时间与最迟开始时间相等","考点:双代号网络计划时间参数的计算。当网络计划的计划工期等于计算工期时，总时差为零的工作就是关键工作。当工作的总时差为零时，其自由时差必然为零。工作的总时差等于该工作的最迟开始时间与最早开始时间之差。参见教材P54",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]