[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108638":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108638,783,1,"单选题","下列关于时标网络计划的编制方法，说法错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","时标网络计划宜按各项工作的最迟开始时间编制",true,{"key":16,"text":17,"correct":18},"B","在编制时标网络计划时应使每一个节点和每一项工作尽量向左靠",false,{"key":20,"text":21,"correct":18},"C","在编制时标网络计划之前，应先按已经确定的时间单位绘制时标网络计划表",{"key":23,"text":24,"correct":18},"D","必要时，还可以在顶部时间坐标之上或底部时间坐标之下同时加注日历时间","考点:时标网络计划的编制方法。时标网络计划宜按各项工作的最早开始时间编制。参见教材P59",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]