[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108635":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108635,783,1,"单选题","在工程网络计划中，关键线路是指（ ）的线路。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","双代号时标网络计划中无波形线",true,{"key":16,"text":17,"correct":18},"B","单代号搭接网络计划中时距总和最大",false,{"key":20,"text":21,"correct":18},"C","双代号网络计划中由关键节点组成",{"key":23,"text":24,"correct":18},"D","单代号网络计划中由关键工作组成","考点:时标网络计划中时间参数的判定。双代号时标网络计划中的关键线路可从网络计划的终点节点开始，逆着箭线方向进行判定。凡自始至终不出现波形线的线路即为关键线路。参见教材P62。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]