[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108634":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108634,783,1,"单选题","某工程双代号时标网络计划如下图所示，其中工作E的总时差和自由时差为（ ）周。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","均为0",false,{"key":16,"text":17,"correct":14},"B","均为2",{"key":19,"text":20,"correct":21},"C","分别为2和0",true,{"key":23,"text":24,"correct":14},"D","分别为2和1","考点:时标网络计划中时间参数的判定。本网络计划的关键线路为C→D→G→I，E的自由时差为0周，总时差为波浪线2周。参见教材P62。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]