[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108633":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108633,783,1,"单选题","时标网络计划的坐标体系不包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","计算坐标体系",false,{"key":16,"text":17,"correct":14},"B","工作日坐标体系",{"key":19,"text":20,"correct":14},"C","日历坐标体系",{"key":22,"text":23,"correct":24},"D","时间坐标体系",true,"考点:时标网络计划的坐标体系。时标网络计划的坐标体系包括计算坐标体系、工作日坐标体系、日历坐标体系三种。参见教材P64",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]