[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108632":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108632,783,1,"单选题","为缩短工期而采取的进度计划调整方法中，不需要改变网络计划中工作间逻辑关系的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","将顺序进行的工作改为平行作业",false,{"key":16,"text":17,"correct":14},"B","重新划分施工段组织流水施工",{"key":19,"text":20,"correct":21},"C","采取措施压缩关键工作持续时间",true,{"key":23,"text":24,"correct":14},"D","将顺序进行的工作改为搭接作业","考点:网络计划的优化。网络计划优化的基本方法是在不改变网络计划中各项工作之间逻辑关系的前提下，通过压缩关键工作的持续时间来达到优化的目的。选项ABD，均改变了工作间的逻辑关系。参见教材P66",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]