[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108631":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108631,783,1,"单选题","网络计划优化时，工期优化应优先选择（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","压缩关键工作且优选系数最小的",true,{"key":16,"text":17,"correct":18},"B","压缩关键工作且优选系数最大的",false,{"key":20,"text":21,"correct":18},"C","压缩非关键工作且优选系数最小的",{"key":23,"text":24,"correct":18},"D","压缩非关键工作且优选系数最大的","考点:工期优化。网络计划工期优化的基本方法是在不改变网络计划中各项工作之间逻辑关系的前提下，通过压缩关键工作的持续时间来达到优化目标。选择关键工作压缩其持续时间时，应选择优选系数最小的关键工作。参见教材P67。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]