[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108629":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108629,783,1,"单选题","工程网络计划资源优化的目的之一是为了寻求（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程总成本最低条件下的资源均衡安排",false,{"key":16,"text":17,"correct":14},"B","资源均衡使用条件下的最短工期安排",{"key":19,"text":20,"correct":14},"C","资源使用最少条件下的合理工期安排",{"key":22,"text":23,"correct":24},"D","资源有限条件下的最短工期安排",true,"考点:资源优化。网络计划的资源优化分为两种：（1）资源有限，工期最短；（2）工期固定，资源均衡。参见教材P75",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]