[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108628":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108628,783,1,"单选题","工程网络计划“资源有限，工期最短”优化的目的是为了寻求（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","资源均衡使用时的最短工期安排",false,{"key":16,"text":17,"correct":14},"B","最短工期条件下的资源均衡安排",{"key":19,"text":20,"correct":14},"C","最低成本时的最短工期安排",{"key":22,"text":23,"correct":24},"D","资源有限条件下的最短工期安排",true,"考点:资源优化。网络计划的资源优化分为两种，即“资源有限，工期最短”的优化和“工期固定，资源均衡”的优化。前者是通过调整计划安排，在满足资源限制条件下，使工期延长最少的过程；而后者是通过调整计划安排，在工期保持不变的条件下，使资源需用量尽可能均衡的过程。参见教材P76。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]