[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108627":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108627,783,1,"单选题","在单代号搭接网络计划中，关键线路是指（ ）的线路。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","持续时间总和最长",false,{"key":16,"text":17,"correct":18},"B","时间间隔均为零",true,{"key":20,"text":21,"correct":14},"C","时距总和最长",{"key":23,"text":24,"correct":14},"D","由关键节点组成","考点:单代号搭接网络计划。单代号搭接网络计划可以利用相邻两项工作之间的时间间隔来判定关键线路，即从搭接网络计划的终点节点开始，逆着箭线方向依次找出相邻两项工作之间时间间隔为零的线路就是关键线路。参见教材P83。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]