[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108626":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108626,783,1,"单选题","关于建设工程多级网络计划系统的说法，错误的有（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","计划系统由不同层级网络计划组成",false,{"key":16,"text":17,"correct":18},"B","能够使用一个网络图来表达工程的所有工作内容",true,{"key":20,"text":21,"correct":14},"C","进度计划通常采用自顶向下，分级编制的方法",{"key":23,"text":24,"correct":14},"D","能够保证建设工程所需资源的连续性","考点:多级网络计划系统。多级网络计划系统是指由处于不同层级且相互有关联的若干网络计划所组成的系统。在该系统中，处于不同层级的网络计划既可以进行分解，成为若干独立的网络计划；也可以进行综合，形成一个多级网络计划系统。参见教材P84。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]