[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108624":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108624,783,1,"单选题","网络计划的资源优化分为两种，其中“工期固定、资源均衡”是指（ ）的优化。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","在工期不变的条件下，使资源投入最少",false,{"key":16,"text":17,"correct":14},"B","在满足资源限制条件下，使工期延长最少",{"key":19,"text":20,"correct":14},"C","在工期不变的条件下，使工程总费用最低",{"key":22,"text":23,"correct":24},"D","在工期不变的条件下，使资源需用量尽可能均衡",true,"考点:资源优化。“工期固定、资源均衡”是指在工期不变的条件下，使资源需用量尽可能均衡。参见教材P76",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]