[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108623":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108623,783,1,"单选题","相对于某工作而言，从网络图的第一个节点（起点节点）开始，顺箭头方向经过一系列箭线与节点到达该工作为止的各条通路上的所有工作，都称为该工作的（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","先行工作",true,{"key":16,"text":17,"correct":18},"B","先做工作",false,{"key":20,"text":21,"correct":18},"C","后续工作",{"key":23,"text":24,"correct":18},"D","后做工作","考点:先行工作和后续工作。相对于某工作而言，从网络图的第一个节点（起点节点）开始，顺箭头方向经过一系列箭线与节点到达该工作为止的各条通路上的所有工作，都称为该工作的先行工作。参见教材P37",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]