[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108621":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108621,783,1,"单选题","工作的总时差是指在不影响（ ）的前提下，本工作所具有的机动时间。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","本工作最早完成时间",false,{"key":16,"text":17,"correct":14},"B","紧后工作最早完成时间",{"key":19,"text":20,"correct":21},"C","网络计划总工期",true,{"key":23,"text":24,"correct":14},"D","紧后工作最早开始时间","考点:网络计划时间参数的概念。总时差TFi－j（TFi）：在不影响总工期的前提下，本工作可以利用的机动时间。自由时差FFi－j（FFi）：在不影响其紧后工作最早开始时间的前提下，本工作可以利用的机动时间。参见教材P45。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]