[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108617":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108617,783,1,"单选题","网络计划中，工作总时差是本工作可以利用的机动时间，但其前提是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","不影响紧后工作最迟开始",true,{"key":16,"text":17,"correct":18},"B","不影响紧后工作最早开始",false,{"key":20,"text":21,"correct":18},"C","不影响紧后工作最早完成",{"key":23,"text":24,"correct":18},"D","不影响后续工作最早完成","考点:网络计划时间参数的概念。工作的总时差是指在不影响总工期的前提下，本工作可以利用的机动时间。参见教材P45。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]