[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108616":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108616,783,1,"单选题","工程网络计划中，某工作持续时间为5天，其3项紧后工作的最迟开始时间分别为第7、8和10天，则该工作的最迟开始时间是第（ ）天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1",false,{"key":16,"text":17,"correct":18},"B","2",true,{"key":20,"text":21,"correct":14},"C","4",{"key":23,"text":24,"correct":14},"D","5","考点:网络计划时间参数的概念。本工作最迟完成时间等于其紧后工作最迟开始时间的最小值，本工作最迟完成时间减去本工作的持续时间即为本工作最迟开始时间，LSi-j=min{LSj-k}-Di-j=min{7，8，10}－5=2（天）。参见教材P45。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]