[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108614":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108614,783,1,"单选题","关于双代号网络计划中关键工作的说法，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","关键工作的最迟开始时间与最早开始时间的差值最小",true,{"key":16,"text":17,"correct":18},"B","以关键节点为开始节点和完成节点的工作必为关键工作",false,{"key":20,"text":21,"correct":18},"C","关键工作与其紧后工作之间的时间间隔必定为零",{"key":23,"text":24,"correct":18},"D","自始至终由关键工作组成的线路总持续时间最短","考点:双代号网络计划时间参数的计算-节点法。选项B错误，以关键节点为开始节点和完成节点的工作不一定为关键工作；选项C错误，关键工作与其紧后工作之间的时间间隔不一定为零；选项D错误，关键线路持续时间最长。参见教材P54。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]