[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108612":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108612,783,1,"单选题","在双代号网络计划中，当计划工期等于计算工期时，如果某项工作的开始节点和完成节点均为关键节点，则该工作（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","总时差和自由时差必然相等",true,{"key":16,"text":17,"correct":18},"B","自由时差必然为零",false,{"key":20,"text":21,"correct":18},"C","总时差必然为零",{"key":23,"text":24,"correct":18},"D","一定为关键工作","考点:双代号网络计划时间参数的计算。以关键节点为完成节点的工作，其总时差与自由时差必然相等。参见教材P54",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]