[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108611":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108611,783,1,"单选题","在某工程双代号网络计划中，如果以某关键节点为完成节点的工作共有3项，则该3项工作（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","全部为关键工作",false,{"key":16,"text":17,"correct":18},"B","至少有一项为关键工作",true,{"key":20,"text":21,"correct":14},"C","自由时差相等",{"key":23,"text":24,"correct":14},"D","总时差相等","考点:双代号网络计划时间参数的计算。以关键节点为完成节点的工作，其总时差和自由时差必然相等。这只能判断每项工作各自的总时差和自由时差相等。参见教材P54。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]